New Campus - ECS Along the River

On Thursday, July 16, the ECS Board of Directors approved a motion to relocate its Middle and High School programs to a new facility located at 743 Technology Drive (currently the Elmhurst Innovation Center) along the Monongahela River. Transition to the new campus is anticipated to occur in advance of the 2027-2028 School Year.

Read the Full Announcement

Preliminary Drawings

Early architectural plans for the proposed campus: floors 1 and 2, floor 3, and the attic.

Preliminary architectural drawings for the proposed ECS Middle School and High School at the Elmhurst Innovation Center

View the Full Drawings (PDF)

Key Dates

Where the proposal stands and what comes next.

June 8, 2026

Zoning presentation

The proposed EC Middle School and High School was presented to the City of Pittsburgh's Zoning Board. View the presentation

June 17, 2026

Board recommendation

The Board of Directors officially recommended relocating Middle and High School programs to 743 Technology Drive. Board presentation

July 14, 2026 

Special Board Meeting and vote

The Board considered the recommendation at a special Board Meeting which was held on Tuesday, July 14 at 5:30 p.m. That meeting was recessed and will continue on Thursday, July 16 at 2:00 p.m. You can watch the Live Feed here at that time. 

2027-2028 School Year

Anticipated transition

If approved, the move to the new campus is anticipated in advance of the 2027-2028 School Year.

About the Elmhurst Innovation Center

Aerial drone view of the proposed new campus building at the Elmhurst Innovation Center

Drone footage of the proposed new campus building. Watch the video

Located along the Mon River, the EIC campus offers many benefits:

Two unique schools with separate entrances and dedicated space with their own principal, administrative staff, teaching and support teams
Modern labs, maker space, digital studio space, cafeteria, gymnasium
Strong outdoor learning opportunities connected to the environmental mission
Access to the Monongahela River
Room to continue expanding programs
Elmhurst Innovation Center campus photoElmhurst Innovation Center campus photoElmhurst Innovation Center campus photoElmhurst Innovation Center campus photoElmhurst Innovation Center campus photoElmhurst Innovation Center campus photo

Plans and Documents

Everything shared so far, in one place.

Full Announcement

The complete June 17 relocation announcement from ECS leadership.

View

Preliminary Drawings

Early architectural plans for floors 1 and 2, floor 3, and the attic.

View (PDF)

Zoning Board Presentation

Presented to the City of Pittsburgh's Zoning Board on June 8, 2026.

View

Board of Directors Presentation

The recommendation as presented to the Board on June 17, 2026.

View

Announcement Video

Watch the announcement of the proposed new campus.

Watch

Drone Footage

Aerial video of the proposed new campus building.

Watch

Additional information and resources: ECS Family Survey  ·  More FAQs

Frequently Asked Questions

Why do we need a new location?

The lease ECS currently has for the middle school is ending in 2028. As we looked at alternatives, we considered how moving the Middle School and High School together could offer opportunities for expanding and improving our programs while also simplifying management and saving some expenses. The Elmhurst Innovation Center provides many benefits and turned out to be the best option available. Our other schools also have space challenges. There are seven years remaining on the lease with the Primary School and ECS will need to figure out what's next for it. The Intermediate School is our flagship school and, as such, we will not move from it. We do need to invest in the facility. Many people, including Facilities, are thinking about that re-investment.

What criteria did you use in selecting the site?

Please see the More FAQs document for additional details.

How will students get to the new location?

Pittsburgh Regional Transit (PRT) serves the site. The average ride time for current students is approximately 46 minutes. The nearby Great Allegheny Passage and Eliza Furnace Trail allow for access with an exit right across the street, with pedestrian signalization at the traffic signal. There are also as many as 250 parking spaces available.

If you search for the site with Google Maps, currently there is a problem with filtering that shows incorrect route information. To resolve this, take the following steps. Open Google Maps and input the address 743 Technology Drive (15219). Click "Directions". Input your home address. Select "Public Transit". When routes are provided, select "Options". Under "Routes" select "Less Walking". Close the "options" window. You can also select specific arrival or departure times under "Leave Now."

What does the new location offer?

The indoor space at the Elmhurst Innovation Center is 89,211 sq.ft., which will allow for 42 classrooms at or more than 800 sq.ft. Specialty spaces could include a literacy lab, remix lab, robotics lab, and hydroponics, along with a gymnasium and cafeteria. There is also ample open space immediately outside of the facility for out the door learning opportunities and programs. There is a two-acre lot adjacent to the facility, and open space across the state. There are also a number of nearby opportunities for out the door learning including the Monongahela River, the Great Allegheny Passage, Hazelwood Green, and South Shore Park.

Moreover, at this new location ECS would be better positioned to serve students from all across the City of Pittsburgh and adjacent school districts. And we would have enough space to increase enrollment. In a new facility, ECS could add as many as 150-200 more students for a total of approximately 650-700 students between the two programs.

What's the process?

At the June 17th Meeting of the Board of Directors, ECS officially recommended the relocation of its Middle and High School Programs to a new facility located at 743 Technology Drive (currently the Elmhurst Innovation Center). The Board will consider the recommendation and vote on the proposal at a special Board Meeting which will be held on Tuesday, July 14 at 5:30 p.m. at ECS Middle School. If agreement is reached, transition to the new campus is anticipated to occur in advance of the 2027-2028 School Year.

What will happen to the Hamilton Avenue property?

If we are successful in negotiating a lease for the Elmhurst Innovation Center, ECS will evaluate the possible uses of the Hamilton Avenue property and make a recommendation to the Board of Directors.

Engage With Us: Comment and Ask Questions

Our promise to you is to be transparent and open about this process.

This webpage is part of that commitment. We will continue to update it frequently, and will provide additional opportunities for you to engage as well.

Board of Trustees MeetingsEmail the CEOSchedule Time with the CEO